The 7 Processes of PRINCE2 Project Management
posted by John Spacey, February 09, 2011PRojects IN Controlled Environments (PRINCE2) is a process-driven project management method.
The PRINCE2 methodology breaks projects into stages and each stage is managed separately. There are 7 processes for managing the project and project stages:
1. Starting up a project
The project team is assembled, the project approach is decided and business justification is documented.activities: assemble project management team, create project brief, agree upon project approach, plan for project initiation phase
check points: the project board approves the next phase of the project (project initiation)
2. Initiating a project
Project planning work is continued.activities: document the project plan, business case, risks, project controls and the plan for the next stage of the project.
3. Directing a project
The project board (project sponsors) controls the project. This involves a series of authorizations, giving ad-hoc direction and confirming project closure.check points: project board authorizes project initiation, stage plans and exception plans
4. Controlling a stage
The project is broken down into stages and each stage is controlled separately.activities: progress assessments, managing issues, status reviews and reporting, taking corrective actions, issue escalation, receiving completed work packages.
check points: work packages are authorized
5. Managing stage boundaries
Includes end of stage activities and planning for the next stage. Also decides what should be done for stages that have exceeded tolerance levels.activities: stage planning, updating the project plan, updating the business case, updating the risk log, reporting the end of the stage end, creating a exception plan.
6. Managing product delivery
Managing the acceptance, execution and delivery of project work. Ensures that the work products are delivered to expectations and within tolerance.activities: accept a work package, execute a work package, deliver a work package.
7. Closing a Project
Project wrap up.activities: formally de-commission the project, project evaluation, identify follow up actions
PRINCE2 Project Management in 90 Seconds Quick 90 second overview of PRINCE2 - a popular project management methodology. |
Recently on Simplicable
Change Management Guideposted by John SpaceyA guide to managing change at the organizational, program, project or team level. |
Corporate Language As A Strategyposted by Anna MarJoining a new firm is often a bit of a language challenge. |
Reverse Logistics Explainedposted by Anna MarHow to handle returns, surpluses, trade-ins and disposals in a supply chain. |