Pending | Work that hasn’t been planned, scheduled or approved. |
In Planning | Planning work is underway. |
Awaiting Approval | A project, task or activity that is planned but not approved. |
Scheduled | Work is approved and scheduled but not stared. |
Not Started | Work that isn’t scheduled to start yet. |
On Track | Within budget, scope, schedule and risk expectations. |
In Progress | Indicates something is happening but is vague about targets. |
Active | Equivalent to in progress. Indicates something is happening without saying things are on schedule. |
Delayed | Indicates things are behind schedule and may be overbudget. |
Issue | Indicates that things are not on track due to an issue. |
At Risk | Highlighting a risk to project completion or possible cost and schedule overruns. |
Off Track | Communicates that a project or task is failing to conform to plan. |
Overdue | Directly indicates deliverables that are late. |
Overbudget | Directly flags cost overruns. |
Incomplete | Work was delivered that didn’t meet requirements. |
On Hold | The project, task or activity is paused. |
Contingent | A project element that can’t move forward until an issue is cleared. |
Blocked | Indicates someone or something is preventing things from moving forward. |
Critical | Indicates a critical issue that requires immediate attention is holding things up. |
Canceled | The project, task or activity is canceled and will no longer be pursued. |
Delivered | Work that has been delivered. |
Submitted | Work that is completed but not accepted. |
Completed | Work that has been accepted as complete. |
Closed | A project that has been completely wrapped up and closed. |